        <article-title>Project Sponsorship in Recovering Delayed Projects: A Case Study from Korek Telecom</article-title>
      </title-group>
      <contrib-group content-type="author">
        <contrib contrib-type="person">
          <name>
            <surname>Mohsin</surname>
            <given-names>Soha</given-names>
          </name>
          <email>sohamohsin@wrec.uoqasim.edu.iq</email>
          <xref ref-type="aff" rid="aff-1"/>
        </contrib>
        <contrib contrib-type="person">
          <name>
            <surname>Qahtan</surname>
            <given-names>Fadia Adnan</given-names>
          </name>
          <email>fadiaadnan@wrec.uoqasim.edu.iq</email>
          <xref ref-type="aff" rid="aff-2"/>
        </contrib>
      </contrib-group>
      <aff id="aff-1">
        <institution>2Assistant, Lecturer, College of Engineering</institution>
        <country>Iraq</country>
      </aff>
      <aff id="aff-2">
        <institution>Al-Qasim Green University, Babylon 51013</institution>
        <country>Iraq</country>
      </aff>
      <history>
        <date date-type="received" iso-8601-date="2026-03-05">
          <day>05</day>
          <month>03</month>
          <year>2026</year>
        </date>
      </history>
    <pub-date pub-type="epub"><day>03</day><month>03</month><year>2026</year><volume>11</volume></pub-date></article-meta>
  </front>
  
  
<body id="body">
    <sec id="heading-da7c28e0a46a52f5d865ec445443cd60">
      <title>Introduction</title>
      <p id="_paragraph-8">In the dynamic field of project management, Throughout the project lifecycle, project sponsors act as important stakeholders by offering guidance, supervision, and executive assistance [1]. In times of crisis, when projects are prone to delays, uncertainty, and a decline in stakeholder confidence, their engagement becomes even more crucial [2]. Project success frequently depends on more than simply resources and planning; it also much depends on how well leaders, such the project sponsor, do their duties. Projects in a variety of industries experienced extensive delays as a result of the COVID-19 outbreak and political unrest throughout the Middle East. One of the industries most affected was telecommunications, where efforts to improve processes and roll out infrastructure were severely disrupted.</p>
      <p id="_paragraph-9">The COVID-19 pandemic, in conjunction with the political instability that existed in many locations, posed difficulties that had never been seen before in the implementation of the project [3]. Such disruptions have had a significant effect on industries like telecommunications in Iraq where large-scale infrastructure projects rely on dependable funding, steady supply chains, and governmental consistency [4]. During this time, one of the major projects for the national telecom company Korek Telecom encountered serious delays. The research is about process change and improving quality. Therefore, no consultant needed from outside the company. All details in the project scope will be managed by the Korek Telecom project sponsor and the rest of the project team. The main objective of this paper is to present possible solutions to overcome the issue of the delayed project at Korek Telecom as well as brining consistency to the process. This study is guided by the following research question: In times of crisis, how can project sponsors manage the recovery of delayed projects while maintaining organizational consistency and process quality?</p>
      <sec id="heading-c5cbd1f2c453a61c103ef745bfc02e46">
        <title>Literature Review<bold id="bold-2"/></title>
        <p id="_paragraph-10">
          <bold id="_bold-7">2</bold>
          <bold id="_bold-8">.1 The Role of the Project Sponsor </bold>
        </p>
        <p id="_paragraph-11">Project sponsorship is identified as a crucial component of project delivery success, especially for high-risk or delayed projects. [5] explains that project sponsor has the responsibility of maintaining executive-client contact because he/she is usually considered from the executive level. [6] stresses that the sponsor's role is not an easy one since it involves much more than just approving deliverables or finances. In order to guarantee alignment with organizational objectives, a project sponsor must act as a strategic champion for the project, offering vision, direction, and continuous support. Successful sponsors are supposed to aggressively remove obstacles that could obstruct the project's advancement, push for the resources that are required, and keep the project team and senior leadership informed. However, [7] argue that some sponsors are passive and are unnecessary in some projects. They explain that some project sponsors micromanage, some can even be aggravating  by getting involved in project details/ decisions while other sponsors prioritise other tasks within the project. On the other hand, [6] explain the challenges the project sponsor has to endure in the project lifecycle. Some of those challenges include insuring projects are being managed well along with the organisation, project manager and the project team are all performing as required.</p>
        <p id="_paragraph-12">
          <bold id="_bold-9">2</bold>
          <bold id="_bold-10">.2 Team Building and Motivation </bold>
        </p>
        <p id="_paragraph-13">High-performing teams are essential in navigating crises and overcoming delays. [8] argue that project managers need to concentrate on fostering a sense of purpose among the different team members in addition to goals. The five stages of [9] team lifecycle, forming, storming, norming, performing, and adjourning, remain essential to comprehending team growth. Group dynamics can be successfully managed by managers and sponsors who match their leadership approaches with these phases. Another important factor in project recovery is motivation. [10] cites Herzberg's two-factor approach, which distinguishes between motivators and hygiene elements. Although financial incentives are not always the best motivator, commitment is frequently increased by trust, justice, and personal development. [11] emphasize the importance of psychological safety and respect, especially in environments of rapid change.</p>
        <p id="_paragraph-14">
          <bold id="_bold-11">2</bold>
          <bold id="_bold-12">.3</bold>
          <bold id="_bold-13">Risk and Conflict Management </bold>
        </p>
        <p id="_paragraph-15">The COVID-19 pandemic's quick spread and severe effects on a number of Middle Eastern nations highlighted how vulnerable commercial, industrial, and educational projects are by nature; many of these projects were canceled or significantly delayed. The necessity of contingency planning has been brought to light by COVID-19, an unpredictable global crisis. Project managers and decision-makers must prepare for unforeseen events by creating strong alternative plans [12]. Most academics agree that projects are nevertheless prone to delays or alterations due to strategic realignments, scope variations, constraint revisions, or shifting milestones, regardless of how much preparation is done [13]. Furthermore, two enduring factors, effort and uncertainty, inevitably shape all projects, regardless of their size, complexity, or scope. This aligns with Murphy's Law, which emphasizes that "whatever can go wrong will go wrong, and most likely at the worst possible time," as well as Parkinson's Law, which states that "work expands to fill the time allotted" [14]. These facts highlight how important it is to conduct a systematic risk assessment at every stage of the project, especially when developing information technology (IT). In order to reduce the possibility of project failure, risk assessment makes it easier to identify, plan, track, analyze, control, and communicate any risks in an organized manner. In support of this perspective, [15] emphasize the importance of incorporating extensive risk evaluation and conflict resolution techniques into project management, showing that the application of three essential risk assessment components can dramatically lower the probability of failure and improve project success overall.</p>
      </sec>
    </sec>
    <sec id="heading-f11006979cc158c347263f791ed90cae">
      <title>Methodology </title>
      <p id="_paragraph-16">This study adopts a qualitative, practice-based case study design to investigate how project sponsorship influences the recovery of a delayed internal project. The ongoing process improvement project at Korek Telecom provided the empirical foundation for this study. The project was led within a balanced matrix organizational structure, meaning the project sponsor and functional managers shared project authority. No external consultants were engaged, and all roles were filled internally. Data were collected from internal project documentation, planning artifacts (business case, project schedule Gantt chart, RACI matrix), and iterative review cycles throughout the 25-day project window. </p>
      <p id="_paragraph-17">A revised business case was created in order to realign the project (Table 1). This document defined goals and deliverables, explained stakeholder roles and approvals, and identified the conflicts that caused the delay. Additionally, it set the project's goal of restoring process consistency and quality in a shorter amount of time. The sponsor-led decision-making process was based on the business case, which offered a well-organized justification for recovery measures as well as a transparent process for gaining support from stakeholders.</p>
      <table-wrap id="tbl1">
        <label>Table 1</label>
        <caption>
          <title>
            <bold id="_bold-14">Table 1</bold>
            <bold id="_bold-15">:</bold>
            <bold id="_bold-16">Business Case for Korek Telecom</bold>
          </title>
          <p id="_paragraph-19"/>
        </caption>
        <table id="_table-1">
          <tbody>
            <tr id="table-row-6350bc2016922bdf0f50d5421aa7c090">
              <td id="5cc27e4b38294662258e6ff2648049ec">Section</td>
              <td id="63d431b98faab499efb5b8aecf7c90c4">Details</td>
            </tr>
            <tr id="table-row-115a219451e75c6510fa75bc1d643b2e">
              <td id="ac0e302d3774daf04bd9e9749f213b0e">Project Title</td>
              <td id="c05e119e8080ea3ae5e3e6fb0a01af8c">Korek Telecom</td>
            </tr>
            <tr id="table-row-06e24ded402abde3df06a6bdb00ec3ac">
              <td id="83804f70b7a524bb4b3d174bf35b287f">Project Duration</td>
              <td id="e051d444264df331212aedbc326d82ea">25 days</td>
            </tr>
            <tr id="table-row-23b9a34b8ce7498545674592fa1ec206">
              <td id="90dc49e258c6f4c3b211bb00e70c1c45">Conflict</td>
              <td id="829522ecc05858535726675a15ea254d">COVID-19 pandemic and political instability delayed the telecom system project</td>
            </tr>
            <tr id="table-row-2a21897b7ad08fd514556b4177da748c">
              <td id="62e98fcdb23d2409f631d3f8bbfd9b8f">Objectives</td>
              <td id="4651b94c1ac82fc8f4fa20ab81167385">1. Identify causes of project delay2. Analyze variances and gaps3. Regain stakeholder confidence4. Develop revised project plan with contingencies5. Establish KPIs and RACI matrix6. Increase awareness of quality</td>
            </tr>
            <tr id="table-row-a598b9ceae04cedf0e757d95b2eef407">
              <td id="7877fa4b6437449056ba6b4c02fd0ff2">Aim</td>
              <td id="c1426c20e4eab151c9104b14129d7ae5">To maintain good project quality and process consistency</td>
            </tr>
            <tr id="table-row-ec47bd88b3d3ee27816c3dd0b1350fd7">
              <td id="381c4a18799207365730963f62a8d646">Deliverables</td>
              <td id="c38eef3d985920da3bccf577616d4b56">Data collection and analysis, revised business case, new plan process; work instruction map; KPIs and controls</td>
            </tr>
            <tr id="table-row-ee643ad613aed2d11472261205ecaaa5">
              <td id="4876cc9f2623807129410f3d10b54a38">Risks</td>
              <td id="d67bb4bf55b68ba58ea84e3e18d114da">Compliance risks; stakeholder dissatisfaction</td>
            </tr>
            <tr id="table-row-bb033a288cc8fb2b5bb3adb397565b3f">
              <td id="386eb5ec7f1cd6eda9e5b2e8833d4e35">Stakeholders</td>
              <td id="8f1cef191716cfb075c297a6166de188">CEO, Project sponsor, Project manager, Staff, Suppliers, Marketing, Security, Engineering lines</td>
            </tr>
            <tr id="table-row-17637e2a33eed6db34967ce26328a9a3">
              <td id="5a0d06f9485e33fb4785827a61b30aa3">Milestones</td>
              <td id="879931482c4afd2ca76da2678f755dc7">Confirm team → Build matrix → Identify gaps → Release new plan → Close project</td>
            </tr>
            <tr id="table-row-2ecc63c3bc724f8a482d0f6fb2f41d97">
              <td id="9a888196bcbeb61126066e2d66f7fca6">Budget</td>
              <td id="c887b66b5e5b1bd56b509c3e4a361758">No procurement required</td>
            </tr>
            <tr id="table-row-b805e9c33924e99fb86593c945dd18a9">
              <td id="a8cd14534a5b4bceda8450acf0788f1e">Approvals</td>
              <td id="493d11c48df9e54bac5ea50a535e1780">CEO, Sponsor, Steering Group, Project Manager</td>
            </tr>
          </tbody>
        </table>
      </table-wrap>
      <p id="_paragraph-20">The business case was then converted into manageable steps using the Work Breakdown Structure (WBS) (Table 2). By dividing the project into four stages, the WBS made sure that sponsor oversight governed every step of the process, from the first diagnosis of the delay to the planning of corrective actions, the implementation of improvements, and, finally, closure. Tasks like developing a risk register, training employees on the new procedure, and negotiating approval procedures with the CEO were all part of each phase. Regaining control of the delayed project required the sponsor to systematically monitor progress and step in at crucial checkpoints, which was made possible by the WBS's hierarchical structure.</p>
      <table-wrap id="tbl2">
        <label>Table 2</label>
        <caption>
          <title>
            <bold id="_bold-17">Table 2</bold>
            <bold id="_bold-18">:</bold>
            <bold id="_bold-19">Work Breakdown Structure (WBS)</bold>
          </title>
          <p id="_paragraph-22"/>
        </caption>
        <table id="_table-2">
          <tbody>
            <tr id="table-row-3a39658223e561a1b217bcebb37b5af6">
              <td id="413c930143b006c9832ebc482949819a">Phase</td>
              <td id="8f9ff269c37e01b7890bec616cd4228b">Task Code</td>
              <td id="6dccf6033af77e43ac314a9503bb90a8">Task</td>
              <td id="165b0b7935addf21265e4210cad3bdd6">Description</td>
            </tr>
            <tr id="table-row-aad21bd908b110013ccefa2bc4c6fdfd">
              <td id="e16be859bd610d12f9490f95caf51f36">Phase 1</td>
              <td id="441e6e87e942f7913292718ccc68cfba">1.1</td>
              <td id="338d6573c241f4c1350065fcfe802ed9">Opening meeting</td>
              <td id="c7afe2b7cf79f9f0e6a3aacd8f25763b">Explain project conflicts and agreed outputs</td>
            </tr>
            <tr id="table-row-216848989eeafd6264d06664babcfa08">
              <td id="26a84dc9f0d7000e35d54ebe7303eaa3"/>
              <td id="c4c37924f8935fbe05c10459892e077e">1.2</td>
              <td id="b2b59f04920bcdad77b0dd4bc7870752">Confirm team</td>
              <td id="aa4706ff2057e5f748bd73984a0dee60">Agree on job assignments</td>
            </tr>
            <tr id="table-row-94c6b3a10f3b3e2875f92a42d0250169">
              <td id="94289631d87ad61726ee8cc68f0a408a"/>
              <td id="a8ee0309f6ebb58909af9c8d0033f416">1.3</td>
              <td id="a58546ba767239f44649c00fe37ce1b9">Negotiate/review creation process with CEO</td>
              <td id="37923332d0f62a72a668f16d94212610">Review and understand creation process</td>
            </tr>
            <tr id="table-row-c1d299321bf5d0cd43aead55f5904751">
              <td id="a01ec15586b4b6195818f816f983e597"/>
              <td id="3921aaff4a220d5e9db6a2f29f903494">1.3.1</td>
              <td id="70ce648ef91b9b2fe47b312713e825e1">Negotiate/review approval process</td>
              <td id="37796546f26dd5e40d9b3b9fc71c75bf">Understand approval process</td>
            </tr>
            <tr id="table-row-fea63ab95c9a5804561faa563694e4fa">
              <td id="b5ea0b92b1ab4bbf248088769dbdd0d4"/>
              <td id="b2fd783b1d0efc0a6909d918871a6a56">1.4</td>
              <td id="37b0e4e350a52e1ef6653573e4c09c15">Gather data</td>
              <td id="6bc9b21657bc06671a1fe48d1edd93b0">Collect information about delays</td>
            </tr>
            <tr id="table-row-edb40cbe81e6100d46de1f7a46e94008">
              <td id="84c0011128e6d61517c8d6267ca895d3">Phase 2</td>
              <td id="fb84bf00a6316d6b48c22ed55402b149">2.1</td>
              <td id="b3019773d877f5719db7241b6f9661bb">Build metrics</td>
              <td id="ba7291056dd162466eab21f7d83c0c11">Develop statistics/charts</td>
            </tr>
            <tr id="table-row-6b0f25442a8929cfe0dd281a2ee7d3e6">
              <td id="d1a7f8e6b7e5c2bd5e30d721c9e617b9"/>
              <td id="d4c506161f735a908143f64aa8d3236c">2.1.1</td>
              <td id="59f768705c0b72c91522e1c08980b6a5">Create map</td>
              <td id="02e119c17d4a9bad5312e7ce36ddc400">Understand current process</td>
            </tr>
            <tr id="table-row-a8b2ac04c8bdb3db88ddfe2a252af98a">
              <td id="2777773ea372fb0243683c16ff3b0619"/>
              <td id="8d32011cfe6b18b408443a7b3955330b">2.1.2</td>
              <td id="4d55645704c70a779523058f665e2c4d">Identify causes/gaps</td>
              <td id="24816eae10b1cfe188d3482ec1c5e24a">Diagnose reasons for delay</td>
            </tr>
            <tr id="table-row-668226b3dfff9ad8fcf67b1214cd79b8">
              <td id="0464a0722ee44251120423c2b3912325"/>
              <td id="a3e1b7401d5f6f7f3ad30279c1892071">2.1.3</td>
              <td id="233c7c27fbe8894e78c1ddfc61a6cc6d">Identify new process</td>
              <td id="5be7d217dda27e60ebc0b083ee3776be">Propose improvements</td>
            </tr>
            <tr id="table-row-d0fedd2207c919a210f653b5f79e1a4d">
              <td id="d4248f9085db091dd521bd068d6f30db"/>
              <td id="230ffdf9450ad445e3aab2f046fcef99">2.2</td>
              <td id="ee41d2bd36fc428ea106fc6cce750093">Create work instruction</td>
              <td id="82d012844845a9b57c16aca00405b957">Develop new procedure</td>
            </tr>
            <tr id="table-row-81785dc82bc81e36cfc5d4d9778d6964">
              <td id="e1263deb122909319bf8813499bca400"/>
              <td id="8c1f37c6a9894566ba424d3b60c8f01c">2.3</td>
              <td id="5b0f1ce493df26dd1a7253ef5258e0aa">Create RACI</td>
              <td id="10ebc2a6e9cfefe05a70e85d047580ab">Define roles</td>
            </tr>
            <tr id="table-row-d0a142381ab857fdba49e6519bfa772b">
              <td id="eea9dc0b0235eba7144fce8244dc51e4"/>
              <td id="5b0067dce6672d9a0833521cd6897aff">2.4</td>
              <td id="79dc6ce4c065a6f3f93b54b37a3509b8">Create risk register</td>
              <td id="debfc40d5b24adbfd20b1a0b0050da8e">Manage risks</td>
            </tr>
            <tr id="table-row-8bb9c428d810676216ef51ec05e2238a">
              <td id="9f7ad45c10d8f973c570eed09ea221b1"/>
              <td id="7bbc044b4d4882cb23fccc2bec353d81">2.5</td>
              <td id="f13d98449ed5d93a0a42e2476c17fcbc">Train new process</td>
              <td id="61b1d339d24be82879061f9715eec9eb">Train staff</td>
            </tr>
            <tr id="table-row-3176bcff4e963fb9fc3f989a884626cd">
              <td id="3e2951ac472fe1907cad46e9720d9e50">Phase 3</td>
              <td id="002dad6b8098ffbe6dbd627bfe46fa0d">3.1</td>
              <td id="e127b00f8369df407fdbcc2059b46877">Apply new process</td>
              <td id="8cc0b102b9585494968eb5cfa22fab98">Implement improvements</td>
            </tr>
            <tr id="table-row-740cf4005fb4c3326ef795c94c145a5b">
              <td id="02e701f463d22034d4abe1f756e7d114"/>
              <td id="f5ea9c77a4bb2d50893cf1a7ef96955c">3.2</td>
              <td id="abbffc911f6156c34306fc79e18a6f99">Review data</td>
              <td id="a118adfeb45aa1b1422487bf1bdf3507">Collect and analyze new process results</td>
            </tr>
            <tr id="table-row-301c4ea77bd577e9d5f58591b8a18dc8">
              <td id="f9e4658b86d06c28cfd3fa69cbf2a6ad"/>
              <td id="6bc25c88eda6fcafd5fe1ffee13efac4">3.3</td>
              <td id="c61849d04f45b6173a07e41268fd1c9b">Modify</td>
              <td id="695fbd7da5b89033874f153f8ecd4a9b">Fix issues as needed</td>
            </tr>
            <tr id="table-row-579253cf44ef09bae85bebb1b2a04508">
              <td id="f0ae420c3e26a36f150ca1c40d4d1a64">Phase 4</td>
              <td id="957dff3631bca21f830ae1974c81ec7b">4.1</td>
              <td id="4177c71bfc338186d0871261543416d4">Close project</td>
              <td id="077e8ff268cd051806859cac1bdeadf5">Finalize if deliverables are met</td>
            </tr>
          </tbody>
        </table>
      </table-wrap>
      <p id="_paragraph-23">The conventional Gantt chart was replaced with a timeline table to handle scheduling (Table 3). In addition to assigning responsibilities and specifying start and end dates, this schedule permitted task overlap when expediency was required. For instance, in order to reduce the recovery window, data collection and process mapping were carried out concurrently with cause identification. Time compression techniques and the sponsor's proactive involvement in making sure dependencies were properly managed were highlighted in the timeline. This table illustrates how a quicker recovery plan without sacrificing quality was made possible by sponsor involvement.</p>
      <table-wrap id="tbl3">
        <label>Table 3</label>
        <caption>
          <title>
            <bold id="_bold-20">Table 3:</bold>
            <bold id="_bold-21">Project Schedule (Timeline) for Korek Telecom</bold>
          </title>
          <p id="_paragraph-25"/>
        </caption>
        <table id="_table-3">
          <tbody>
            <tr id="table-row-fa9adb6552ffa78dc1ce057850d3d4b6">
              <td id="988b5dfabaf9806d4156ad19035374e4">Phase</td>
              <td id="b1254d7a18ecbd727f62c10de2ad7cde">Task No.</td>
              <td id="a169fe0fae345eeee0f08155e3d822ec">Task Description</td>
              <td id="8aa363067a8a6abcb08cecf8901c0e2c">Start Date</td>
              <td id="5b43e03337127f70c475edab06931b8d">Finish Date</td>
              <td id="dccdd5c13e90f15393b55eda628f889a">Responsible Roles</td>
            </tr>
            <tr id="table-row-7e084efd52a7a22adb45683cf34711e4">
              <td id="7e09a2cb40462e0cb36efd75ba899e46">Phase 1</td>
              <td id="1161d56fecc3dcc50d1629c3d6969e73">1</td>
              <td id="b7e5d47a2cc9f3b4e60ebb6de7b8b24b">Opening meeting</td>
              <td id="585ac7a4233d190611ee55a17065e358">1/12/2024</td>
              <td id="b771cc297a6999dd473227ea9a16323f">1/12/2024</td>
              <td id="6e1855b92fa4b8406a42ea199789a1d9">All</td>
            </tr>
            <tr id="table-row-075e28a07d7b16879eee3dc5de612290">
              <td id="fa607c8a5e4386ddd66c685bf98a3a67"/>
              <td id="76865c9c7c25bf96b1214cbd264b947f">2</td>
              <td id="83b0e172ee71080d4d0003aad2cf00c0">Confirm team and attendance</td>
              <td id="76db0b2159a78c3037ef93e24189acad">1/12/2024</td>
              <td id="d6ec15b30c63214943b9aa11d5925d0e">1/12/2024</td>
              <td id="c771701c2087727f62bb5b8189508c06">All</td>
            </tr>
            <tr id="table-row-c01338b76295f2320b64cb3c641154d3">
              <td id="442d90d177859529fc3a0a1309f1fec0"/>
              <td id="3d005fffdc1da533f1952c0991157c0b">3</td>
              <td id="855a9ed956b2c9800dcb0b8f4717c111">Negotiate/review creation process with CEO</td>
              <td id="362700657892be75a879c8e3dc34132c">1/12/2024</td>
              <td id="c1b0c23d4bd990e03ac13544b0324438">2/12/2024</td>
              <td id="67299c0ebad5dd833badc90aad05f5b2">PS, PM</td>
            </tr>
            <tr id="table-row-6d0c8e5a7dca3804ab1cd9e978c470ad">
              <td id="ee9ef5aeb5d2bd51c98c2eeb943e609c"/>
              <td id="b44ee80096362d7dba04056f48cfe013">4</td>
              <td id="64167484796a363dd0ca5250a637a1dd">Negotiate/review approval process with CEO</td>
              <td id="b958988b7699ccdb916684ae76a97bac">1/12/2024</td>
              <td id="c7bd33cee2e12974cab64733bc4e6cf6">3/12/2024</td>
              <td id="521089720d1d65a40473c0a8076e855f">PS, PM</td>
            </tr>
            <tr id="table-row-979a8f793b0ac59de576a295b0d6654e">
              <td id="2519d6cf02e93b003258cd664439b587"/>
              <td id="1555ae595c0a0356924dabad811bb3cd">5</td>
              <td id="87f922bf3ae28a9a4122de53a665c48f">Gather data</td>
              <td id="f1a3e2fb07051254165fc72cb8665755">4/12/2024</td>
              <td id="0c28db367d4757786969172655991130">7/12/2024</td>
              <td id="8ce0ed120b2730a941257f6dc31c877f">PM</td>
            </tr>
            <tr id="table-row-a4f6b019cda02a733bce72e209f29fac">
              <td id="7e70424e504e0d970543a98e3eb04f13">Phase 2</td>
              <td id="cf3182d40e3c0018c6c20849607d5991">6</td>
              <td id="f02dd5c73085225e71ebb98fa16ff29c">Build metrics</td>
              <td id="1e1ea570d65270462b4196f120638cc9">8/12/2024</td>
              <td id="b01b3571d9333104d8b910b2b4b65d1a">9/12/2024</td>
              <td id="0fd37dffc1f0e84eeac360964af05551">PM</td>
            </tr>
            <tr id="table-row-6e781714d6cbf89aa5b498d408e05cf8">
              <td id="3b758739c3f15223e7a3397fea5ed702"/>
              <td id="c2c2b9b5282c905463eba17578693655">7</td>
              <td id="13762722eee7089b6b1b52899e0cfda9">Create process map</td>
              <td id="fd102ee102cce48c4c2be7890532d728">10/12/2024</td>
              <td id="b8cc63d93e9bf69b05da856b879178fa">11/12/2024</td>
              <td id="0ec9810ef1a42bdf36208667e3196be4">CEO, PS, PM</td>
            </tr>
            <tr id="table-row-9d119c451a164a7804673654b87966d1">
              <td id="3d55002dde2d31410705ac33ee43ca62"/>
              <td id="c91eeb5cfc8c52dd6f07717dee8832c0">8</td>
              <td id="058fc39eb870bdc1f835c41af200def7">Identify causes and gaps</td>
              <td id="64bff60d6ccccad8879e309e50a7f5b9">12/12/2024</td>
              <td id="ffb5b6bbc8765e93eafb47a0399f3520">13/12/2024</td>
              <td id="6e5cb59eb2b01787432b195612c7cd53">PS, PM</td>
            </tr>
            <tr id="table-row-366ddb94b7f6dbcf57716538c0518709">
              <td id="181ee07ace51819dc0eb1436c1ded9e1"/>
              <td id="0802f9e2c256a402871f4d28e6827574">9</td>
              <td id="dbbd5d21015d374188aedf6f3816e262">Identify new process</td>
              <td id="c1f1869b72005968ae694dd2c39a42f0">12/12/2024</td>
              <td id="aaa184b5a9563d28a71faef302a117f1">13/12/2024</td>
              <td id="f23b3b71f74fc219e3e11427098bf178">All</td>
            </tr>
            <tr id="table-row-221aec04e4a08b150e3bd2b88f3421ad">
              <td id="dcf71895f4665d7be18c67ba1709de81"/>
              <td id="0a948fdd7aef2c1bbe121f1c1c6dbcd3">10</td>
              <td id="9e3ded44269edfa5fdd3902dedb9c3c0">Create work instruction</td>
              <td id="2d8e35424009f2a236acfa5b271bc8ac">15/12/2024</td>
              <td id="eb272d76231c24c20c158263b5311887">16/12/2024</td>
              <td id="396159ffe911814ace19606ecf004db5">PM</td>
            </tr>
            <tr id="table-row-938afcd92da2c7f8fe0c08253c547443">
              <td id="418451b6c19824a4952965f641a7d4ee"/>
              <td id="bb2ba9d5572fdc1ed07fb9cc5cdc16fa">11</td>
              <td id="dba1d6e972328a1bb5c72fbb4def7a44">Create RACI for new process</td>
              <td id="8e8bf5b39273db7221a71bfdad8e8267">17/12/2024</td>
              <td id="5b00c550eb927cebee3a90cc4c12b267">18/12/2024</td>
              <td id="64544e89b3aa9fea8c72fa535f840d8b">PS, PM</td>
            </tr>
            <tr id="table-row-09f4e6c0daf6f2e0c3a67c56578cb41c">
              <td id="af60246d87ed6371bdfca4a3f43a973e"/>
              <td id="b807901aaa91f1fb6cc76396402b0c64">12</td>
              <td id="64f134796b9d06039d83df27b410a666">Create risk register</td>
              <td id="9854e3781396b6f5de0743aa846ec82f">19/12/2024</td>
              <td id="07dbe121b692a5e0c0141682d078ec8a">20/12/2024</td>
              <td id="39844120810d42cba9632fdfe4069992">PS, PM</td>
            </tr>
            <tr id="table-row-44d54f04bdd0442a5466279a4c9c0f64">
              <td id="b9055cdf253d88a6552c637de1d40cbf"/>
              <td id="61a17933b570d9b9fac2ddade81f3679">13</td>
              <td id="7d66d79987c55f70888625dfedc6e9dd">Train new process</td>
              <td id="ed5e73cf10a36bfb617bc28d1df0b5da">21/12/2024</td>
              <td id="752638019a602e9044929a74e56fc668">21/12/2024</td>
              <td id="8f34450ebe93a6ea73fa214fe93548ca">PM</td>
            </tr>
            <tr id="table-row-f3080a3ae692dea4e3be7698df20d146">
              <td id="095304d12310b6062dbe210bbb39159b">Phase 3</td>
              <td id="b6c4ef3680d4635250a79bfb58c215ab">14</td>
              <td id="1c307c98eeda00fb8fc85e0e0e0b3cd1">Release new process</td>
              <td id="9d5a783c6650dc9eb9aeec8db665cae1">20/12/2024</td>
              <td id="69c3a46b36d3d159d003613c0c377ac8">21/12/2024</td>
              <td id="db341bc151feb8a120c020e359327200">All</td>
            </tr>
            <tr id="table-row-6cb3c6a9eb73f312af2a4aa21a562b4e">
              <td id="9e9bf25df7f214331ecb25dafb3d40ac"/>
              <td id="ba30f0b517b8bad686be107e935ed028">15</td>
              <td id="06828af8cd71c9163b3e0d43d2121cf7">Gather/review new data</td>
              <td id="ec2fa00b46f1e5510f4877bb9d0e5f97">21/12/2024</td>
              <td id="2d75e33e025abd6b8d80fdc4b366c387">22/12/2024</td>
              <td id="b06fa173bf9a641615ed1ec40b5d3033">PM</td>
            </tr>
            <tr id="table-row-36d73b21a3139b231dcf59c6faa08f2b">
              <td id="dc025f749138c5f8b081f2a2d774526a"/>
              <td id="421450f72e054adf3c6c90fade22f3c4">16</td>
              <td id="b553728c475a9dbaa22555429c6a00f4">Modify process</td>
              <td id="5c9ff99a38cfb7c166229ee01c0b5af0">23/12/2024</td>
              <td id="e380a65f0f7735d18df98578e4a90087">24/12/2024</td>
              <td id="f29322ff729e29637cbd0da35ffedbe2">All</td>
            </tr>
            <tr id="table-row-57b83465704b926d1edbfb0a313e9b1f">
              <td id="6e4a99a2c88b536ead8b3e0cd61a8c72">Phase 4</td>
              <td id="f3da00809d00e58208fbac96614ae880">17</td>
              <td id="c9ee3c968f1248fec095ef23c2c43b61">Close project</td>
              <td id="f2f98ced5ecf208b5fff93571bfe3f8d">24/12/2024</td>
              <td id="6905ba9a4b2a0d96d020623031a4037c">25/12/2024</td>
              <td id="24bc2cc47d66eda54057b43afc1f8f42">All</td>
            </tr>
          </tbody>
        </table>
      </table-wrap>
      <p id="_paragraph-26">A RACI matrix  (Table 4) was created in order to make accountability clear. For every significant task, this tool designated who was in charge, accountable, consulted, and informed. The sponsor's central leadership role was reinforced by their positioning as (Accountable) for crucial tasks, while the CEO retained oversight and approval authority. By establishing clear decision-making processes for the executive, sponsor, project manager, and steering group, the matrix reduced ambiguity. In matrix organizations, where role overlap can cause confusion, this was especially crucial. The sponsor's pivotal role in the recovery process was highlighted by their accountability for deliverables like data analysis and process mapping.</p>
      <table-wrap id="tbl4">
        <label>Table 4</label>
        <caption>
          <title>Table 4. RACI Matrix</title>
          <p id="_paragraph-27"/>
        </caption>
        <table id="_table-4">
          <tbody>
            <tr id="table-row-6176c110879bbf4c2f891bd52f079c0e">
              <td id="2e0834d05d9a5bf743519960075745fe">Activity/Deliverable</td>
              <td id="989c67d0fd4193af2b83d26748a1a185"/>
              <td id="72272ad368851c63edcc22803b090bac">Project Sponsor</td>
              <td id="435f418cdf54ea9c0d0214096004f5fd"/>
              <td id="fcccda7f009b5ee13eff5337db6b6de5">CEO</td>
              <td id="12cbab9e79fe26d3f6880d8d89edbb70">Project Steering Group</td>
              <td id="6805727613e206378ebdd570510b38ca"/>
              <td id="9691a364dc14a28ed5b665a11206b91b">Project Manager</td>
            </tr>
            <tr id="table-row-3ed988c87a565a5cc85addde467c4453">
              <td id="3fe137e4dba4e039d983694c7ad3e44c">Collect/review data</td>
              <td id="3a842c236186c031494fd754c740fa6e"/>
              <td id="eee26e847563a69ff885e3ca189900c7">A</td>
              <td id="4a50a163af6b88bb6105205f4a100934"/>
              <td id="3bf889a87b688ffa3bcbdb8d9ed64459">R</td>
              <td id="c2bf0d88a6a2cf8189c232fbf6bf3c86">I</td>
              <td id="7c088c31c83dcff47016d73fc9d9b3e0"/>
              <td id="6e0897b36b5e9af56dbfee0ecd495ab1">—</td>
            </tr>
            <tr id="table-row-e6764907affb1952b7e2867a1256b7e8">
              <td id="10cee87a8107aff20e86f179dfb55f4c">Analyze causes/solutions</td>
              <td id="d88fae315973f6011c5f9bda2df87213"/>
              <td id="e08ea1ec6d85d887da721499fe8be918">—</td>
              <td id="3c81be147fcdead1a590bd20a9b4e37f"/>
              <td id="51ce460497bb6858ef4f3c1469f974da">R</td>
              <td id="4998b32b74ccda411a8d37ada8770c0e">A</td>
              <td id="c31a6acb061c5ae1c95eaa2865089204"/>
              <td id="241380121eeafb7bfb605cbcccc4800d">I</td>
            </tr>
            <tr id="table-row-b5c1dd4a392085487355e9fd1d308e16">
              <td id="43f8887e8977324a5b9d3952ade63b69">Map process</td>
              <td id="bccd8b9f827756a687c21a334c90b83b"/>
              <td id="534559a06ba7514fc32f1cdd9aaaa546">—</td>
              <td id="964dce1d266e6474d490bfc833741e33"/>
              <td id="d07cd7487112cd2039c5b864608a74fa">R</td>
              <td id="254cb48abcd48a124b13a8de482e75b7">C</td>
              <td id="ddbbf56010bc6345c2f3c98cc0d011dc"/>
              <td id="23dd73e73cc0300b77721e2c1397b4d8">I</td>
            </tr>
            <tr id="table-row-d9c28308203c20e6f9b4e0677ee202ee">
              <td id="60bdbdab26f40f464e9157cd6a9ec651">Develop business case</td>
              <td id="629d93045bf28e632145bd3d3f82bed6"/>
              <td id="2cb51cde92469185494645305a04a0da">—</td>
              <td id="33148b462aa4088921c4a4597a26aac7"/>
              <td id="48894248bc5d090bdfaeb7b61d9f857d">R</td>
              <td id="1fad54c79c4b718bc72c95ad9d68dcb6">C</td>
              <td id="9142b45e3e3af109f124dfcfa92a23b9"/>
              <td id="a7c656aa335741aa5a2b99379a1b4021">I</td>
            </tr>
            <tr id="table-row-bf1995b0c972e3c4656fa2a82b56fe46">
              <td id="db9f4fe7e8d3deee295b68ebf1308d82">Agree on improvements</td>
              <td id="9ab1765d36250cae1d6d48f7ed01ec42"/>
              <td id="9e53a711b9495ef4f14ddc3bdb98a127">—</td>
              <td id="fa7a21138450a863d0ae4c0542d90333"/>
              <td id="2719f794fd1a33854304ec95bc9944d3">R</td>
              <td id="dd63d0359fe0729ee7b7fe017ab8909a">C</td>
              <td id="ef8179ec92dd23e87b28ae7d102213c5"/>
              <td id="63932be00d8c090ca0028919214d8d75">I</td>
            </tr>
            <tr id="table-row-a07d333e70cec46444fcaea5af607cba">
              <td id="5a1775f6bcaf8570884e49a5c0726df1">Initiate work instruction</td>
              <td id="322a1e0327cce32931e9b2b1f46af23b"/>
              <td id="332c8b9674e4aaf02fba5df2d06fa763">—</td>
              <td id="b2ddb5b3630c8402c5d2fd1dbd95a309"/>
              <td id="23010bb8532ce42f6fa059d238c302a3">R</td>
              <td id="84b743148e474c5a5c084802d58ea943">A</td>
              <td id="45fc61a274f5ee0c3368d32e442485f2"/>
              <td id="bee842ea84312e03604dbcfa52c0939d">I</td>
            </tr>
            <tr id="table-row-19e5f53a17e765315031ae5bd820834e">
              <td id="d5d07d9852113a0c23d4f12222b5ae94">Build metrics</td>
              <td id="1e87913f2f5ae1335ab84adb1f629fa9"/>
              <td id="1baf8140bfa3972723a318c842caf80a">—</td>
              <td id="c4cda9d6d9229136b5630e16d340eb53"/>
              <td id="0ee03d46ff69ab7334ad794f8bfad1ca">R</td>
              <td id="638d2484a62f1c32ca7d7b7d2002b2f4">A</td>
              <td id="67e8675ff996c94b2891a864b8ec7bdf"/>
              <td id="8a47964abe655945da5270d614431f7b">I</td>
            </tr>
            <tr id="table-row-88526ec574c4c253c3b114994ed451c8">
              <td id="0ef76f775a8bd3878317e498bd582b98">Release new plan process</td>
              <td id="a34a69fc9522549292a4d9960f7029db"/>
              <td id="ac10ef8099e9a2783eafb5ce2d688061">C</td>
              <td id="40478890ca0c79bf356823cadb431121"/>
              <td id="905a4c3de9e322a4c14559b8c4c2b940">R/A</td>
              <td id="b370749d9c0c218c2977ecf9eecebd2a">R</td>
              <td id="ebfd0c43ae55402eecebbe000e7bb552"/>
              <td id="7aeb70e1bb0be1addc95dc810ec36140">A/I</td>
            </tr>
            <tr id="table-row-c4cf084e614b6b9824ae14a01906b43e">
              <td id="ca3c48a8c410c354c0784ee16b974ab0">Develop methods for control</td>
              <td id="83686dda1cc1e343cbfe53b9da3ca37d"/>
              <td id="db6f2aeffe533bf03f4ec8bf0c2c8ed8">I</td>
              <td id="849b8147322c08ac66fcb027c187e0fd"/>
              <td id="be3e91c02c8a6b883ea74cfc854d3494">R</td>
              <td id="fc018655947aade21cbb8745f8e0b45f">A</td>
              <td id="1787f6b8672f56ab15a129f16c4f4448"/>
              <td id="d94f210db9158073541304de703ae9d5">I</td>
            </tr>
            <tr id="table-row-17ddf04baf6d03a424ba4a75797493e9">
              <td id="74e59e5242b7a57463605e91c904493c">Modify process</td>
              <td id="73e614ce1bda8990aa0b3bfa8a49ccdd"/>
              <td id="1f6896c814c1dac1eb28991deb2f7711">—</td>
              <td id="30d4cd6466bf94298677df3d323797a7"/>
              <td id="6c29b0bcbaac5771ca7cd8df3778e78d">R</td>
              <td id="0a259c602fe31925c7b3a450d9ed1a53">A</td>
              <td id="fe0d86e4e03fe7b7b329483e6ec2e568"/>
              <td id="10e05417f0ddc8213e068ca975f1b8c2">I</td>
            </tr>
            <tr id="table-row-d50723d6644007da09301872fbd1ed11">
              <td id="f0cf55351406388c2bf98a28f22119ea" colspan="7">Key: R = Responsible, A = Accountable, C = Consulted, I = Informed</td>
              <td id="240c6df28a82dc2d089dd4afe2913bf8"/>
            </tr>
          </tbody>
        </table>
      </table-wrap>
      <p id="_paragraph-28">In order to foresee and reduce risks to the recovery plan, a Risk Register was created (Table 5). This included risks like limited technical expertise, staff resistance to change, and incomplete data. Every risk was given a responsible owner, evaluated for impact and likelihood, and accompanied by mitigation techniques like executive briefings, training sessions, or contingency buffers. Promoting risk mitigation was greatly aided by the sponsor, especially when it came to executive support and stakeholder alignment. The project team made sure that uncertainties were actively managed rather than allowed to impede the recovery process by institutionalizing risk management.</p>
      <table-wrap id="table-figure-6e0c9af2c127d7156271c0a523b02197">
        <label>Table 5</label>
        <caption>
          <title>Table 5: Risk Register</title>
          <p id="paragraph-1f93e42dfbb5af756159c7f4eef46e83"/>
        </caption>
        <table id="table-0d5e506f27921cabfcfc8aa5d557574c">
          <tbody>
            <tr id="table-row-21f1db8be2883eb7956412ab34c2bed0">
              <td id="table-cell-13b97fa500e9c4e0903e8ba144a08e93">Risk ID</td>
              <td id="table-cell-fbe8f707305779c6994f73ced1ee9147">Description</td>
              <td id="table-cell-c629490ae4589cf4c43f52d948265798">Likelihood</td>
              <td id="table-cell-da0ddd66f837d8647dc7965bd7684ad6">Impact</td>
              <td id="table-cell-f22223874b023788ba428f86a3ad023f">Risk Level</td>
              <td id="table-cell-5b8a097dedaa2131a4671b6829024554" colspan="3">Mitigation Strategy</td>
              <td id="table-cell-12e3e25de6e21012db94758eb669f8fc" colspan="2">Owner</td>
              <td id="table-cell-08572ecd909e2f2c9f6e63ae55a43dc2">Status</td>
            </tr>
            <tr id="table-row-4d03459a254d85297fddab6c75bd1c59">
              <td id="table-cell-9099eee32b483c946c67b9bb66bb2a42">R1</td>
              <td id="table-cell-46496e9cde16329dd5657ae08f55026d">Staff resistance to process changes</td>
              <td id="table-cell-fe43a33f8035b1fd69879804a07988bc">High</td>
              <td id="table-cell-9cafffe3de6c7e194514c18d2e1d3c09">High</td>
              <td id="table-cell-c35d40f567b472c9416d0878db8045e1">High</td>
              <td id="table-cell-0e7c01e2d296a3561201f3a9d8ab8a27" colspan="3">Conduct change management workshops; involve staff in planning stages</td>
              <td id="table-cell-f854f52fcea7c33597bda9f0d1d87728" colspan="2">Project Manager</td>
              <td id="table-cell-34534e665a6d58607d201921d6ddd0f5">Open</td>
            </tr>
            <tr id="table-row-9216a3f96a69ced5074aef06780ed83f">
              <td id="table-cell-5a4d43b469993145e8a2657442b125ca">R2</td>
              <td id="table-cell-b8e11c249ee952be25ce15d680cba252">Lack of executive support</td>
              <td id="table-cell-f72b3376ecc28e6298acda8b0eabccf0">Medium</td>
              <td id="table-cell-86d54765c689d5daf84b31098699c0be">High</td>
              <td id="table-cell-a3270ea9129de72bad66efd5ce0a6b32">Med-High</td>
              <td id="table-cell-eca57bd2dbbb21810584e28d608b21a3" colspan="3">Engage sponsors early; provide regular executive briefings</td>
              <td id="table-cell-04decd3a7edd2dbe2e0ae1aa3e7eb875" colspan="2">Project Sponsor</td>
              <td id="table-cell-4a26299896fe67b9a32fa10cf68dedcb">Open</td>
            </tr>
            <tr id="table-row-b86460b86cfe09fd826787e2994407f2">
              <td id="table-cell-d61e39820bd3622ec24b9b07821d8527">R3</td>
              <td id="table-cell-cc2021e599e576695241115acb9c65aa">Inaccurate/incomplete data</td>
              <td id="table-cell-2cd4a6eee581dc4c056a5ebd4700e188">High</td>
              <td id="table-cell-7665aaa3c94dc93a208d90ca9274d488">Medium</td>
              <td id="table-cell-df240cb986f21c47cd40539a04ae0e9e">Med-High</td>
              <td id="table-cell-f940abce8ea1170ef70a017f04448327" colspan="3">Use data validation; triangulate with stakeholder interviews</td>
              <td id="table-cell-679e0be734d64a3a37fa44bb73a77232" colspan="2">Data Analyst</td>
              <td id="table-cell-c9375478523a81c77ce06392d15ef535">Open</td>
            </tr>
            <tr id="table-row-51c7fe9c48023c853ce24ed82596d428">
              <td id="table-cell-d80b7e7d5360811f0a8370e11e6a5f4a">R4</td>
              <td id="table-cell-1d0fed58946751efdaa2d1b2cf1bf308">Delays due to overlapping initiatives</td>
              <td id="table-cell-55cb9e46aa88855f4f05d8f80768bdf1">Medium</td>
              <td id="table-cell-3a08e28985883b4ed93117bd000f6f34">Medium</td>
              <td id="table-cell-48d1eff9d4b19c5801167f9ec593f8be">Medium</td>
              <td id="table-cell-317e353fae90d0f18abde6ae21158888" colspan="3">Align timelines; prioritize critical changes</td>
              <td id="table-cell-b9fe54e006cb8697e324857236f89d7a" colspan="2">PMO/Scheduler</td>
              <td id="table-cell-fa0851eeb496ff0370026bf684002371">Open</td>
            </tr>
            <tr id="table-row-eab78b8e29cc29c1fc6b8c260c735ed2">
              <td id="table-cell-72a38ea31a8a3e63520904b68b3c0946">R5</td>
              <td id="table-cell-81078a16c1dc3b0aad6aab1586766d4f">Limited technical expertise</td>
              <td id="table-cell-af94e7529e742623640ee85c87679c4b">Low</td>
              <td id="table-cell-034dcbbc2677d7b826ed8414b75e8880">High</td>
              <td id="table-cell-62820960e746fa03a16a2f2a76d1f782">Medium</td>
              <td id="table-cell-0dc2c118672baae273ec36057f6a1727" colspan="3">Provide training and up skilling programs</td>
              <td id="table-cell-8dcfdc54d101e6561e4a37b0262b635f" colspan="2">HR/Training Lead</td>
              <td id="table-cell-4c512ef19a7dae39e7809033b81b8681">Open</td>
            </tr>
            <tr id="table-row-d30964829a4898408484165c5228f46b">
              <td id="table-cell-68c5f232a47405dc826e07a844519b84">R6</td>
              <td id="table-cell-8d1d2229b0618ee0f41bd383525e2722">Departmental misalignment</td>
              <td id="table-cell-8689f11383bf825d019c3cfae503c5bd">Medium</td>
              <td id="table-cell-43a3f9b980cfa18ad5de20fb5bdd45c9">Medium</td>
              <td id="table-cell-cb13f8449f2380ffcf376ad4b197a478">Medium</td>
              <td id="table-cell-ad90c215795bfdeec4ed88b10b05de2d" colspan="3">Cross-functional team meetings; improve internal communication</td>
              <td id="table-cell-9d6f3ca9ca872129c242963c12fcc78d" colspan="2">Functional Managers</td>
              <td id="table-cell-5644c41274098aafaabdfe842e55487e">Open</td>
            </tr>
            <tr id="table-row-3d5c2272ac664e0cd41ea877b48d8f22">
              <td id="table-cell-684e567f9e8db4c03653a92a95cb5270">R7</td>
              <td id="table-cell-d0296521373b192a838d7f6e16d0b841">Budget overrun</td>
              <td id="table-cell-82b1c5110417cb53cd0efae2f023d3c2">Low</td>
              <td id="table-cell-6b9a69648576a920ad6ae0a59139b3ee">High</td>
              <td id="table-cell-098686e70bbb90a6ca462c5d9c8e4189">Medium</td>
              <td id="table-cell-7392eb9db50052045c264004bec403cd" colspan="3">Add contingency buffer; regularly review estimates</td>
              <td id="table-cell-8b5f7231bf79b8485c6aee6b9def55c6" colspan="2">Finance/PM</td>
              <td id="table-cell-a2054486573fb2ceab212fe48a71ed67">Open</td>
            </tr>
            <tr id="table-row-d9da7538dc21f588f8279f13e5555b8b">
              <td id="table-cell-dc26e4da90e090a45b248ad4bd93db0a">R8</td>
              <td id="table-cell-d35ab412089f83b53fdfba456c22c7d5">Failure to achieve quality improvement</td>
              <td id="table-cell-cfd07ecc0c434db68ace5872bbc115ae">Medium</td>
              <td id="table-cell-cc9291c88317d414240ab90ce7d2f67a">High</td>
              <td id="table-cell-588b35b42001fb0e102011e6d4d341d3">High</td>
              <td id="table-cell-66c91b99307c3e3c1d56fada2b6a8bf2" colspan="3">Define SMART metrics; apply continuous monitoring</td>
              <td id="table-cell-ac1745dad2c6b80218e5be19e8955d94" colspan="2">Sponsor/Team</td>
              <td id="table-cell-ddcad75511d506302c3b7f399584e6b0">Open</td>
            </tr>
          </tbody>
        </table>
      </table-wrap>
      <p id="_paragraph-30">Following a qualitative assessment, risk-reduction measures were created, enabling the team to keep an eye on and address issues like staff resistance, a lack of management backing, and inaccurate data. The study made sure that uncertainties were systematically managed by incorporating sponsor-led governance and structured tools into the methodology. This improved the reliability of project execution as well as the validity of scholarly analysis.</p>
    </sec>
    <sec id="heading-6c997e461bd5e3576a25f1481afe2ce0">
      <title>Findings</title>
      <p id="_paragraph-31">The case study of Korek Telecom demonstrated how proactive project sponsorship can aid in the recovery of a postponed project in times of high uncertainty. Without consulting outside experts, the sponsor-led recovery plan concentrated on streamlining internal procedures and bringing the project into compliance with organizational standards. The sponsor served as the primary leader and coordinator in the well-balanced matrix organization. A revised business case, a thorough Work Breakdown Structure (WBS), a project schedule (Timeline), a RACI matrix for accountability, and a risk register for scope control were among the major deliverables of the plan, which was organized around a 25-day timeframe. The phased recovery plan was described in the WBS (Table 2), starting with team confirmation and concluding with project closure. The sponsor was able to keep an eye on developments and make sure that they were in line with recovery objectives thanks to this organized breakdown.</p>
      <p id="_paragraph-32">The updated project timeline after sponsor intervention is shown in the project schedule (Table 3). A conscious acceleration strategy is reflected in the overlap of execution tasks and the compression of planning activities. The claim that sponsor participation facilitated quicker decision-making and resource mobilization is supported by this timeline. Accountability was redistributed, with the sponsor taking responsibility for a number of crucial deliverables, as shown in the RACI matrix (Table 4). This change helped the team understand expectations and reaffirmed the sponsor's operational role. Key threats, such as opposition to process change and problems with data quality, were recognized and categorized by the Risk Register (Table 5). The sponsor and project team improved control over project outcomes and decreased uncertainty by allocating ownership and mitigation strategies. </p>
      <p id="_paragraph-33">Furthermore, the sponsor modified communication tactics for a remote environment and followed Tuckman's team growth model. Because of COVID-19, communication was conducted through emails and video conversations. By acting as a mediator between the CEO and the project manager, the sponsor prevented a blame culture and restored alignment. Internal stakeholders reported improved morale and increased confidence in the updated plan by the project recovery phase's conclusion.</p>
    </sec>
    <sec id="heading-b460ba7ceec6bb393fb6b436c78cbdd4">
      <title>Discussion </title>
      <p id="_paragraph-34">The study's conclusions highlight the significance of active project sponsorship as a determining element in the recovery of postponed projects. The sponsor had a direct impact on decision-making, stakeholder engagement, and process improvement rather than giving the project manager exclusive authority. This active involvement confirms prior research that highlights the sponsor’s role as a strategic leader [1], [5] while extending it by showing how sponsor-led tools can be operationalized during crisis recovery.</p>
      <p id="_paragraph-35">From a theoretical perspective, the study adds to the body of knowledge on project management by showing that sponsorship is operationally transformative rather than just symbolic. Both strategic direction and daily operational oversight are provided by sponsorship, as demonstrated by the sponsor's role in structuring the WBS (Table 2), leadership in risk identification (Table 5), and consolidation of accountability in the RACI matrix (Table 4). This contradiction advances current discussions about whether sponsors should be directly involved in execution or act at a high level [16]. In practice, the case offers a number of insights for companies dealing with delays brought on by crises. First, teams can refocus and speed up recovery without compromising quality by using structured sponsor-led tools like risk registers, WBSs, and updated business cases. Second, the team's confidence is restored through sponsor-led communication and accountability realignment, which combats the drop in morale and clarity that usually follows project setbacks. Sponsor involvement in scheduling (Table 3) and risk mitigation is particularly important for telecom companies operating in unstable environments because it guarantees process consistency and organizational resilience in the face of outside disruptions.</p>
      <p id="_paragraph-36">However, there are limitations to the study. The analysis may not be as generalizable to other industries or national contexts because it is based on a single case within Korek Telecom. Furthermore, causal relationships cannot be statistically established because the qualitative nature of the research prioritizes depth over breadth. Lastly, even though the project recovered in the allotted 25 days, longer-term effects like the sustainability of process modifications were not assessed. Therefore, sponsor roles in a variety of industries and cultural contexts should be the focus of future research, especially in fields that are highly susceptible to external shocks. The generalizability of these results could be examined through comparative analyses of sponsor-led recovery in energy, construction, and IT projects. The operational impact of sponsorship on recovery timelines and stakeholder confidence may also be confirmed by quantitative research employing survey or performance data. In summary, this study demonstrates that project sponsors can serve as operational leaders who reorganize procedures, reduce risks, and rebuild confidence in times of crisis rather than merely endorsing projects at the executive level. Sponsors can turn postponed projects into chances for process improvement and organizational learning by fusing strategic oversight with hands-on intervention.</p>
    </sec>
    <sec id="heading-173c2da083e5d1d8b93efec1c9ecc66d">
      <title>Conclusion </title>
      <p id="_paragraph-37">This study looked at how important project sponsorship was to Korek Telecom's resolution of a postponed internal project. In order to realign project objectives and rebuild team confidence, the sponsor's leadership in putting tools including a rewritten business case, WBS, Project schedule, RACI matrix, and risk register into place was crucial. The results support the body of research on the value of risk management, team cohesion, and project sponsorship. Organizations can benefit from enhancing the sponsor's position, especially in crisis management and change management, according to practical implications. Future studies might examine sponsor influence in various contexts and industries. In the end, successful sponsorship is a leadership function that promotes recuperation, adaptability, and project accomplishment.</p>